If the Data Center Leaves, Who Pays for the Power Line?

AEP Ohio has one agreement for building the line and another for using it. The customer’s obligations change when the power comes on.

By Victor Julian Hale · Written

An investor can sell an AI share; a utility cannot unbuild a power line with a click. A stock sale does not cancel a data center. But a customer’s departure can leave infrastructure that still needs paying for.

On Thursday, November 19, the Senate passed amended H.R. 2347, 62–33. Its data-center provisions address utility rates for service and necessary grid upgrades. Senate passage alone does not enact them.

Existing contracts deserve attention, too. For covered new projects, AEP Ohio says its Letter of Agreement requires reimbursement of 100% of buildout costs if the customer cancels, or delays more than 12 months, before target energization. That obligation expires when the project is completed. It is not a permanent guarantee covering every regional power line.

The separate service agreement’s term starts when the power comes on. For covered new load, its initial term is at least the ramp-up period (up to four years) plus eight years. Under Ohio Power’s tariff, minimum billing demand after ramp-up uses an 11-month lookback and a tiered capacity test. The 85% cap within one calculation is not an 85% ceiling on the whole bill.

Using less power does not erase the charge for capacity. One early-exit route opens after five post-ramp years, with 36 months of minimum charges due. With a three-year ramp, that option opens after year eight of the contract. A customer may also request reassignment of up to 25% of capacity under conditions, remaining responsible for capacity left behind. These are limited routes out.

Some lines benefit many customers; others principally serve one project. A fair allocation must recognize that difference. These documents establish no particular extra charge on your household bill.

I would ask the utility and its regulator one question before construction: which signed payment obligation survives if this customer leaves? Show the dedicated costs, the shared benefits and any uncovered balance. A promise of economic growth deserves enthusiasm alongside a clear account of who pays if the promise shrinks.